Photo Journal

Here is a chance for you to glimpse the progress we’ve made on the building so far.

Feb 2012 | Jan 2012 | Dec 2011 | Nov 2011 | Oct 2011 | Sept 2011 | Aug 2011 | July 2011 | June 2011 | May 2011 | Apr 2011 | Mar 2011 | Feb 2011 | Jan 2011 | 2010

Feb 2012

By the middle of February RMC will be welcoming many new and returning students. The furniture is being installed in preparation and final interior touches are being made.

Whilst the rain in Sydney has been a consistent obstacle to the builders this summer, they have begun work on the stairs to the new courtyard. The new S Block common rooms are progressing well.

Jan 2012

Now that the new building sits where the student carpark used to be, the ground is being prepared to ashphalt the new RMC student carpark. Final preparations are also being made to the exterior of the building.

At the start of the new year the action is mainly on the inside of the building. The kitchens are being installed, carpet is being laid and walls are being painted.

Dec 2011

In December the remainder of the previous student carpark is being excavated in preparation for the new courtyard.

Nov 2011

In November the exterior walls of the building are being revealed as each layer of scaffolding is removed.

Oct 2011

In October the scaffolding has started to come down and a sneak peek of the new building’s exterior colours is visible. The walls for the new substation that will power the new building behind are also complete.

Sept 2011

On 10 September Macquarie University held its annual Open Day. RMC provided tours of the College which included visiting a display ensuite room in the new building. 1 room down, approximately 101 to go!

Aug 2011

On 17 August another milestone was achieved when the very last concrete slab was poured!

In early August there were only 2 concrete slabs to go – the roofs N and S Block. The view from the back of the College has also changed.

July 2011

In July the scaffolding is reaching to the skies and the building is beginning to peek over the RMC courtyard fence. By the end of the month we were able to have our first look at the inside!

June 2011

In June the building is rising out of the ground and RMC’s driveway has become part of the construction zone.

May 2011

In May the structure of the building is beginning to take shape. The formwork for “S” block has been laid, meanwhile “N” block walls are rising after the first concrete slab was laid. The construction of the staircase for “N” Block has also begun.

Apr 2011

In April the traffic to the new building site has led to some interesting driveway situations. As pictured below, an extremely large concrete pump was required to pour the concrete for the base of a lift that will allow disabled access to all levels of the new building. Concrete has also been poured to create a 100 000L capacity retention tank that, in the interests of sustainability, will eventually collect roof water to irrigate the College grounds.

Mar 2011

On 3 March RMC held a Turning of the First Sod Ceremony. In attendance was Mr Victor Dominello (State MP Ryde), Dr Peter Dodd (Deputy Vice-Chancellor of Macquarie University), Cr Ivan Petch (Deputy Mayor of Ryde), Dr Rob Mackay (Chairman of RMC Board), Prof Chris Bellenger (current Master of RMC), Bishop Paul Barnett (Master of RMC 1979-1989), Assoc Prof Stuart Piggin (Master of RMC 1990-2004).

The very next day, a 30 tonne drill rig reversed down the RMC driveway and the Master’s fence was “relocated”.

Feb 2011

In February, the builders began to move on site.

Jan 2011

At the end of January preparation of the grounds began.

2010

Here are the photos before construction started.